Rakiraki District School rebuilding

  • Underway!

      4 April 2016

    I have spoken with Ashok (the builder from Nadovi Builders) and by email with Mr Navu Maiwaqa (Head Teacher = Principal of the School) today.

    The 'make safe' is now underway and concrete blocks have been ordered. There was a hold up as concrete blocks are currently in very short supply and the builder wanted to do it all in one go; I have now asked the removal of overhanging blocks is done this week. More (new) blocks are expected within 10-14 days, so the main repair will be done then.

    And I am getting a quote of the re-roof and re-wire -to see what's required to get the whole classroom block back to fully operational.

    Thanks for your on-going donations....it all helps!!

    Aksel.