St Mark's Opawa - Repair & Renewal

  • More progress

      16 April 2021
    Main image

    The scaffolding went up and then it was all covered so work could start... especially the removal of asbestos before anything else is done. You can see more photos in the gallery.

      0 comments  |  Login to leave a comment
  • Work now underway!

      19 February 2021
    Main image

    Just shy of the 10 year anniversary of the 'quake, work has now begun on the project. Hallelujah!!

    Unfortunately, the initial engineering plan for the St Anne's Chapel was faulty. The chapel will still be completed as part of the repairs, but we have had to commission some further work on the extension.

      0 comments  |  Login to leave a comment