INFRASTRUCTURE REBUILD FOR MELE VANUATU

MeleMaat Kindergarten Progress Report No.1

  18 May 2015
Main image

Thank you to all the Mele Village supporters - this update has been delayed due to our internet being off line for a week. My apologies.

I can advise that our kindergarten rebuild at MeleMaat is taking shape and over the past few weeks we have completed the block work, have the roofing framing in place and this week (weather permitting) we should complete the roofing.

The progress has been slowed due to weather here in Vanuatu plus local holidays but now the schools are on holiday this week the team should get more work completed towards closing in the build.

We have also completed the toilet block and this should be plastered and finished to take the toilet fittings shortly. Our picture shows the completed toilet block getting an initial plastering and the roofing work being finalised ready for the iron sheeting.

Many thanks for all your support thus far and with our Australian fundraising efforts we can advise that our work for the kindergarten is moving along.